Construction of office buildings with data processing centre
Project objective
“Development of JSC Transtelecom’s infrastructure to provide data centre infrastructure as a service”. “Construction of office buildings with data processing centres in Atyrau, Aktau, Aktobe, Uralsk, Kyzylorda, Zhezkazgan, Karaganda for JSC Transtelecom”.
Mission
Installing, commissioning and starting up all the Data Centre’s engineering systems.
What has been done
Installation of engineering systems for the operation of the data centre, namely category 1 uninterruptible power supply system, automatic fire alarm system, automatic warning system, video surveillance system, ventilation and air conditioning system. Equipment from global manufacturers Schneider Electric, Tesar, Legrand, ABB, Stulz, York, Bosch and others. The work was completed in the shortest possible time.
Specific characteristics: Work was carried out simultaneously in 7 cities.
Result
Commissioning and launch of the data processing centre in 7 cities of Kazakhstan. Increasing the level of digitalization and improving information security (cybersecurity).